Alameda Street Reconstruction Project
Phase 4 is expected to start tentatively February 2028
Location: Alameda Street from Everhart Road to Airline Road
Current Phase: Construction scheduled for November 4, 2026
Council District: 2
Project Type: Bond 2022 Project
Project Timeline: Approximately two years, with five phases
Project Upgrades:
The Alameda Street Reconstruction Project will completely rebuild Alameda Street from Airline Road to Everhart Road in City Council District 2.
The project includes removing the existing roadway and replacing it with durable concrete pavement. Improvements will also include new curbs and gutters, sidewalks, ADA-compliant curb ramps, street lighting, signage, pavement markings, and upgraded traffic signals to improve safety, accessibility, and traffic flow.
In addition, the project will include upgrades to stormwater, water, and wastewater infrastructure to improve the reliability and long-term performance of these essential systems.
Avalon Street and Robert Drive, both adjacent to Alameda Street, will also be reconstructed as part of the project to improve roadway conditions and connectivity throughout the area.
Contractor: Texas Material (formerly Bay Ltd.)
Construction Cost: $15.8 million
Contact Information:
Geoffrey Mayer: 361 446 3015, geoffreym@corpuschristitx.gov
Russell Soike: 361 480-9011, rsoike@agsm.com
Beth Becerra: 361 826-1693, elizabethb3@corpuschristitx.gov
Phase 1 Traffic Map
Construction timeline on Phase 1 is November 4, 2026 to May, 2027

Phase 2 Traffic Map
Phase 2 is expected to start tentatively May 2027

Phase 3 Traffic Map
Phase 3 is expected to start tentatively September 2027 
Phase 4 Traffic Map
Phase 4 is expected to start tentatively February 2028

Phases 5-7 Maps Coming Soon
Project Updates (updated on a biweekly basis):
Project to start November 4th, 2026.